Draft List of Stoppages 2009/2010 issued by British Waterways
for Stratford upon Avon Canal

Location

 

 

 

Days

Details

Brandwood Tunnel

09-Nov-09

to

18-Dec-09

40

Brickwork Repairs (tbc)

Locks 4 and 5

09-Nov-09

to

18-Dec-09

40

Lock 4 New gates plus brickwork repairs, Lock 5 brickwork repairs

Locks 13

16-Nov-09

to

20-Nov-09

5

Principal inspection

Lock 21

04-Jan-10

to

12-Mar-10

68

New Bottom end gates

Lock 23

04-Jan-10

to

12-Mar-10

68

New Top end gates & brickwork repairs to wing walls and lock approach

Lock 32

04-Jan-10

to

12-Mar-10

68

New Top end gates & minor brickwork repairs

Lock 34

04-Jan-10

to

12-Mar-10

68

Refit gates and major brickwork repairs

Culvert 6

04-Jan-10

to

12-Mar-10

68

Major works to repair culvert

Edstone Aqueduct

04-Jan-10

to

12-Mar-10

68

Brickwork Repairs (tbc)

Locks 40, 41, 42, 43, 44 45,46,& 47 Wilmcote

09-Nov-10

to

12-Mar-10

124

Major works on lock chambers plus new gates at Lock 42 and Principal Inspection at Lock 43

Maidenhead Road Lock 53

04-Jan-10

to

08-Jan-10

5

Principal inspection

Warwick Road Lock 55

04-Jan-10

to

12-Mar-10

68

New gates plus brickwork repairs